A B.C. Supreme Court ruling quashed the project's substantial-start decision. The two Nations reject the Tsetsaut Skii km Lax Ha's claims.
By The NWBC Current newsroom
The Nisga'a Nation and the Tahltan Nation have reaffirmed their support for Seabridge Gold's KSM project after a court ruling sent part of its approval back to the province.
On Nov. 18, the B.C. Supreme Court quashed the 2024 decision that KSM had substantially started, a designation that keeps its environmental certificate from expiring. The court found the province had not adequately consulted the Tsetsaut Skii km Lax Ha Nation (TSKLH), and the province must now reconsider after further consultation.
Located in the Golden Triangle roughly 65 km northwest of Stewart, KSM ranks among the largest gold-copper deposits on Earth that have yet to be developed. Seabridge says more than 700 million dollars has gone into site work. In a joint statement, the Nisga'a and Tahltan said the project is in Tahltan territory and the Nass Area, called the TSKLH claims opportunistic and unsupported, and warned that an expanding approach to consultation is creating uncertainty and hurting investment in the northwest.
TSKLH's lawyer said the province's own 2023 assessment found the proposed waste facilities are in TSKLH territory. The Nation says it is not against the mine but wants its rights respected. The Gitxsan Huwilp Government, which withdrew its support for KSM this year, restated its backing for TSKLH.
The B.C. Mining Association estimates Golden Triangle projects could generate nearly 800 billion dollars in activity over two decades. How quickly the province completes the new consultation will matter for mining jobs across the northwest.
Sources: Terrace Standard, Nov. 23, 2026, Global News, Nov. 23, 2026.
You may like
Terrace and 'Ksan Society prepare to turn the overnight shelter into a 24-hour warming centre during extreme cold
Belgian marine firm hired for offshore trenching on the Prince Rupert Gas Transmission line, with work starting next year
Skeena sockeye came in more than a million fish below forecast, and conservation groups want a review before more commercial openings
Trigon finishes structural work on a second Prince Rupert berth, but a propane project is stalled in a legal fight with the port authority
Proposed Kanata floating LNG plant near Prince Rupert signs a planning deal with Korea's Hanwha Ocean
B.C. pump prices are down about 29 cents a litre in a month, but remain above last year's