LNG Canada hires its second tank builder as it asks to flare more gas in Kitimat

VINCI Construction will build the Phase 2 storage tank. A separate permit request to raise flaring limits is open for public comment.

Published Nov 23, 2026 in Kitimat
By The NWBC Current newsroom
Aerial view of Kitimat with the Kitimat Ranges behind and an industrial plume rising over the valley
Photo: Sam Beebe via Wikimedia Commons, CC BY 2.0 (source)

LNG Canada's Phase 2 expansion in Kitimat has its tank builder.

VINCI Construction says it has been hired to engineer, buy materials for and build a second liquefied natural gas tank at the site. The tank will hold 225,000 cubic metres, the same size as the first one, which VINCI finished in 2025. The contract came from the JGC Fluor joint venture that is building Phase 2. VINCI puts its value at about 400 million euros.

Ground clearing for the new tank began as part of early Phase 2 work in October.

The company is also asking the province for room to flare more gas while the plant settles into steady operation. LNG Canada has applied to the BC Energy Regulator to change its air emissions permit. The request would raise the combined routine flare limit by about 10 times.

LNG Canada says flare volumes run higher during early operations and that a problem with one flare tip added to the total. The company says it has cut flaring by about 40 percent over the last six months and is working on a new flare tip.

Some health researchers and the B.C. Green Party leader have pushed back and want a full health review before any change is approved.

The regulator posted the notice on Nov. 12. Anyone who may be affected has 60 days from the notice to send written comments to the company, with a copy to the regulator.

We're still keeping an eye out for more on this story and will update it if anything changes.

Sources: VINCI news release, Nov. 20, 2026 (https://www.vinci.com/en/newsroom/press-releases/vinci-wins-contract-build-lng-tank-canada), CFNR Network, Nov. 23, 2026 (https://www.cfnrfm.com/2026/11/23/lng-canada-to-install-benzene-analyzers-in-kitimat-after-public-concern-contractor-hired-to-install-phase-two-tank-funded-by-indigenous-partnership/), LNG Prime (https://lngprime.com/americas/vinci-scores-lng-canada-tank-gig/200348/), BC Energy Regulator notice, Nov. 12, 2026 (https://www.bc-er.ca/news/environmental-protection-notice-lng-canada-development-inc/), CBC News, Nov. 17, 2026 (https://www.cbc.ca/news/canada/british-columbia/lng-canada-flaring-limit-9.7424624), CFNR Network, Nov. 16, 2026 (https://www.cfnrfm.com/2026/11/16/lng-canada-files-long-anticipated-amendment-to-allow-for-10-times-currently-permitted-flaring-volumes/).